Activity Types
To change the type of a activity, use the drop down list in the Activity Type column.
To see the information that describes the activity, select the ACT Tab in the Details Pane (next to the PFD).
Type | Description |
Project | The top level activity for the project. This
activity generally rolls up all information to a single line. Most
of the information for the project brief can be captured for this activity.
This type allows entry of the following information:
|
Stage (Management) | A stage within a project. At
a minimum, there is an Initiation Stage and at least one other stage.
This information
summarises the work within the stage. The
stage information provides the basis for a stage plan.
This type allows entry of the following Information:
|
Stage (Technical) | A collection of related products and activities that generally deliver a technical set of products. Technical stages are typically within a management stage. These are described in the PRINCE2™ manual. These may relate to design or build iterations.
This type allows the same information as the Stage (Management) above. |
Work Package | A work package to be assigned to an individual
or team manager. This
identifies the products that will be created by the team manager and the
completion requirements for the work package.
This type allows entry of the following information:
|
Create Product | The identification of a specific product to
be created. This
product is linked to the line in the Product Checklist. The
focus of this activity is performing configuration management activities
to work on the product. The
details for this activity relate to the configuration item information.
This type allows entry of the following information:
|
Activity | An activity is a package of work that can be
used anywhere in the project activities list. Typically
the activities relate to the creation of a product.
This type allows entry of the following information:
|
Quality Check | A type of activity to check a product against
the quality criteria. The
collection of these activities form the basis for the Quality Log.
This type allows entry of the following information:
|
Note: Programme and Tranche will be enabled in future releases.